Boulogne Port - Environmental and regulatory studies relating to the Boulogne sur Mer port

Return mosaic

CLIENT: REGION HAUTS DE FRANCE

PROJECT DATE: 2017

LOCATION: Pas-de-Calais (62)- France

MISSIONS:

  • Sensitivity tests
  • Wave propagation model implementation: MIKE SW
  • Port agitation model implementation and residual agitation calculation
  • Field, mesh, and bathymetry
  • Analysis by interest area

BACKGROUND:

As part of the northeastern pier boom reconstruction at the Boulogne-sur-Mer Port, it is necessary to have precise information of the agitation conditions.
The purpose of this study is twofold:

  • It is a question first of all to have the agitation dimensioning conditions for the work;
  • In a second step, the study aimed to verify that the modification of the structure is not likely to significantly increase the conditions of agitation inside the harbor basin, and in particular in the outer harbor, particularly at the lock of the basin afloat (Napoleon basin).

CREOCEAN@CREOCEAN_keran
#Créocéan a réalisé avec @iSeaNews et @nke_Instruments la pose de 2 bouées instrumentées et 2 ADCP avec Atlantiqu… https://t.co/kbT880968F